Process flow: drill in place → Drilling → Mud injection → Run casing → Continue drilling → Slag removal → Hole cleaning → Hoist the reinforcement cage → Water jetting and bottom cleaning → Concrete conduit → Placing concrete → Catheter & rarr; The pile top reinforcement can be divided into single liquid silicification method, double liquid silicification method, aerated silicification method and electric double liquid silicification method.Process flow: drill in place → Drilling → Mud injection → Run casing → Continue drilling → Slag removal → Hole cleaning → Hoist the reinforcement cage → Water jetting and bottom cleaning → Concrete conduit → Placing concrete → Catheter & rarr; The pile top reinforcement can be divided into single liquid silicification method, double liquid silicification method, aerated silicification method and electric double liquid silicification method.
A -m long orifice pipe is installed at the opening of the grouting hole to prevent possible hole collapse. At the same time, it plays a guiding role in drilling. During grouting, grouting pump and the lowered grouting pipe are connected for grouting, and the grouting is carried out according to the requirements. The grouting pump will inject the slurry into the soil. After completing the construction of one grouting section, move the grouting pipe up or down according to the requirements to carry out the construction of the next grouting section.Shi ChuqinGrouting pipeMarket shock will consolidate the operation,2024-02-2702:42:13Special slings shall be used for the lifting of horizontal members such as laminated plates and the stress at each lifting point shall be uniform to avoid fracture due to uneven stress of members. Grouting method is to put some solidified slurry into the cracks or pores of rock foundation in order to improve its physical and mechanical properties. Professional grouting pipe, steel flower pipe, advance small pipe, high-pressure grouting pipe, pipe shed pipe grouting pipe factory, high price, service, on-site settlement and honest management! The purpose of grouting is to prevent seepage, stop leakage, strengthen and correct the deflection of buildings.● specification: inner diameter of secondary grouting pipe: mm; Outer diameter: mm; Inner diameter tolerance: & plusmn; .mm; Length of each roll: m.
Process flow: drill in place → Drilling → Mud injection → Run casing → Continue drilling → Slag removal → Hole cleaning → Hoist the reinforcement cage → Water jetting and bottom cleaning → Concrete conduit → Placing concrete → Catheter & rarr; The pile top reinforcement can be divided into single liquid silicification method, double liquid silicification method, aerated silicification method and electric double liquid silicification method.Push the rock powder and sundries that are not washed,Shi ChuqinSteel pipe, remain at the hole bottom, or stick to the hole wall out of the grouting range, so as to improve the bonding strength and impermeability between the slurry stone body and the fracture surface.Shi Chuqin,Portsmouth,The grouting mechanism includes filling grouting, compaction grouting and splitting grouting. Grouting materials include granular slurry and chemical slurry. Granular slurry is mainly cement slurry, and chemical slurry includes silicate (water glass) and high slurry. Silicification method, alkali solution method, high chemical grouting method and cement grouting method.
share 3 Comments
Comment / Cancel reply